Message-ID: <12288697.1075861340055.JavaMail.evans@thyme>
|
|
Date: Thu, 15 Nov 2001 15:37:03 -0800 (PST)
|
|
From: justin.j.rutherford@williams.com
|
|
To: slc <.williams@enron.com>
|
|
Subject: NWP System Notice - December 2001 Monthly Maintenance
|
|
Mime-Version: 1.0
|
|
Content-Type: text/plain; charset=us-ascii
|
|
Content-Transfer-Encoding: 7bit
|
|
X-From: Rutherford, Justin J <Justin.J.Rutherford@Williams.com>
|
|
X-To: 'abenton@utilicorp.com', 'abenton@utilicorp.com', 'andre.f.robinson@dynegy.com', 'anita.reubens@swgas.com', 'becky.wells@eprime.com', 'bgoddard@semprasolutions.com', 'bharp@coral-energy.com', 'bmantz@semprasolutions.com', Guderian, Brandon <Brandon.Guderian@Williams.com>, 'browning@wasatchenergy.com', 'bruce.langmade@gapac.com', 'bymank@wdni.com', 'cards@wdni.com', 'caver_ealy@pgn.com', 'ccoyle@americansoda.com', 'cdecotea@westerngas.com', 'cmcgra@puget.com', 'cpavlica@enerad.com', 'craig.provenzano@powersrc.com', 'cslaman@usg.com', 'cwduke@duke-energy.com', 'cwojta@national-fuel.com', 'darena@national-energy.com', 'Dave.Dungan@Weyerhaeuser.com', 'deborahs@kimballenergy.com', 'dhuck@reliant.com', 'dlh@nwnatural.com', 'dmyers@enserco.com', 'eric.rost@swgas.com', 'FERMIS@ENRON.COM', 'gary.sanchez@tombrown.com', 'gborrego@semprasolutions.com', 'geek@bp.com', 'gilesmh@bp.com', 'janderson@clarkpud.com', 'jane@itcoworld.com', 'janicew@questar.com', 'jdebruyn@westerngas.com', Owen, Jennifer </O=ENRON/OU=NA/CN=RECIPIENTS/CN=GWADDR/CN=HQ3.EM5.JENNIFER OWEN>, 'jhaake@national-fuel.com', 'jmmcarthur@duke-energy.com', 'jnowell@semprasolutions.com', 'johnru@questar.com', 'joy.toups@elpaso.com', 'jpowell@reliant.com', 'jsanders@clarkpud.com', 'karencu@questar.com', 'katalin_kiss@transalta.com', 'kbuys@westerngas.com', 'kevin.headrick@eprime.com', 'kevinfo@questar.com', 'kims@kimballenergy.com', 'kirk_lundell@transalta.com', 'ksiwak@coral-energy.com', 'llightfoot@coral-energy.com', 'lmansi@sdge.com', 'lorrainehi@questar.com', 'LPRIOR@ENRON.COM', 'markpi@questar.com', 'mbeckner@utilicorp.com', 'mcano@enerad.com', 'melewis@utilicorp.com', Hunter, Michelle </O=ENRON/OU=NA/CN=RECIPIENTS/CN=GWADDR/CN=HQ3.EM5.MICHELLE HUNTER>, 'mmcmahon@avistaenergy.com', 'morgan.doyle@huskyenergy.ca', 'mreed@enserco.com', 'nathan.dougherty@eprime.com', 'painsworth@kimballresources.com', 'pattr@questar.com', 'ramperms@bp.com', 'rcooper@usg.com', 'rcooper@utilicorp.com', 'rfm@nwnatural.com', 'rob_findlay@transalta.com', 'ron.smith@ashgrove.com', 'ron.youell@mirant.com', 'rplatt@duke-energy.com', 'rudesm@texaco.com', Watt, Ryan </O=ENRON/OU=NA/CN=RECIPIENTS/CN=RWATT>, Williams, Kent (SLC) <S.Kent.Williams@Williams.com>, 'sakom@attglobal.net', 'SBREWER@ENRON.COM', 'scott.holloway@eprime.com', 'scott.linkletter@neg.pge.com', 'scotts@kimballenergy.com', 'sghill@bcgas.com', 'spjutd2@wdni.com', 'ssanchez@westerngas.com', 'SSOUTH@ENRON.COM', Brodeur, Stephane </O=ENRON/OU=NA/CN=RECIPIENTS/CN=SBRODEU>, 'tdickers@westerngas.com', 'tdizona@coral-energy.com', 'tinaf@questar.com', 'tkcheeseman@duke-energy.com', 'trevor.cochran@engageenergy.com', 'trevor.cochran@engageenergy.com', YILDIROK, VAL </O=ENRON/OU=NA/CN=RECIPIENTS/CN=GWADDR/CN=HQ3.EM5.VAL YILDIROK>, 'wharlan@kimballresources.com', 'william.brown@swgas.com', 'zcourns@national-fuel.com', 'ads@nwnatural.com', 'BHall@cngc.com', 'bmedlock@cngc.com', 'cheldman@kimballresources.com', 'cpeterso@cngc.com', 'creali@vanalco.com', 'debbie.fortman@swgas.com', 'gary.peterson@gapac.com', 'gastrans@puget.com', 'kdickey@idacorpenergy.com', 'lgoodric@cngc.com', 'marcl@subutil.com', 'mhamme@puget.com', 'MVaughn@cngc.com', 'rernest@intgas.com', 'rsf@nwnatural.com', 'sdoss@wlinpco.com', 'siekasj@osm.com', 'spfaff@cngc.com', 'stu.card@weyerhaeuser.com', 'Tina.m.patton@boeing.com'
|
|
X-cc:
|
|
X-bcc:
|
|
X-Folder: \FERMIS (Non-Privileged)\Ermis, Frank\Inbox
|
|
X-Origin: Ermis-F
|
|
X-FileName: FERMIS (Non-Privileged).pst
|
|
|
|
Post Date: November 15, 2001
|
|
Category: MAINTENANCE
|
|
Subcategory: NWP MONTHLY MAINTENANCE
|
|
Subject: December 2001 Monthly Maintenance
|
|
|
|
Notice Text:
|
|
All Shippers Letter #01-317
|
|
Date: 11/15/01
|
|
Time: 16:30 MST
|
|
|
|
|
|
|
|
TO: ALL SHIPPERS
|
|
|
|
SUBJECT: DECEMBER 2001 MAINTENANCE SCHEDULE
|
|
|
|
The following maintenance work is scheduled on Northwest Pipeline for
|
|
the month of December. Potential system impacts are identified below.
|
|
Volume impact and scheduled maintenance out of service date estimates
|
|
are stated as accurately as possible, but are subject to change based
|
|
on factors such as ambient temperatures, actual market demand, etc.
|
|
Any variance from this notice will be communicated to customers as
|
|
quickly as possible before commencing work. All capacities listed in
|
|
this maintenance schedule are in Dekatherms.
|
|
|
|
|
|
**** Denotes capacity impacts that are in addition to those posted on the Annual Maintenance Letter.
|
|
|
|
|
|
|
|
DECEMBER 2001 MAINTENANCE:
|
|
|
|
|
|
Replace Engine Chocks at the Snohomish Compressor station
|
|
|
|
Date: October 22, 2001 to December 8, 2001
|
|
Design Cap: 720,000 Dth
|
|
Available Cap: 614,000 Dth
|
|
|
|
Replace the Chocks on the units at the Snohomish compressor station. Only one unit will be unavailable at a time during this work. Based on current nominations, which are below available capacity, there is no anticipated impact to customers.
|
|
|
|
|
|
Semi-Annual unit inspections at Sumas Compressor station
|
|
|
|
Date: December 4, 2001 to December 5, 2001
|
|
Design Cap: 724,000 Dth
|
|
Available Cap: 607,000 Dth
|
|
|
|
Perform annual inspections on C Plant units #7 and #8 at the Sumas compressor station. Inspection of unit #7 is scheduled for December 4, and unit #8 is scheduled for December 5. A and B Plants will accommodate any lost capacity. Based on current nominations, there is no anticipated impact to customers.
|
|
|
|
|
|
Semi-Annual unit inspection at Mount Vernon Compressor station
|
|
|
|
Date: December 6, 2001
|
|
Design Cap: 722,000 Dth
|
|
Available Cap: 696,000 Dth
|
|
|
|
Perform annual inspections on unit #3 at the Mount Vernon compressor station. Based on current nominations, which are below available capacity, there is no anticipated impact to customers.
|
|
|
|
|
|
|
|
Please contact your Marketing Services Representative or the Northwest Pipeline Hotline at (801) 584-7301, for further information.
|
|
|
|
|
|
WGP-W
|
|
JR |